Calculating Length Of Adjustment With No Shifts

To Add An Adjustment For A Staff Member, Go To Personnel>Adjustments & Leave:

L 13

Use the options on the left-hand side to select the correct Date Range, Rota Group and Team.

L 14

Click on the appropriate staff member, and press the green plus button:

L 15

This will bring up the Add Adjustment window, input the correct from and to dates and Adjustment Reason. 

If there are no shifts within the Adjustment period and no normal working hours on the Staff Member's Personnel Record then the length will be calculated incorrectly:

L 16

You will then have to edit the duration manually to display the correct length of time:

L 17

If you have added Normal Working Days onto a Staff Member's Personnel Record then the System will calculate the duration based off that information:

L 18